Overnight cost is the cost of building a project, such as a power plant, if no interest had to be paid during construction, as though the whole project were completed instantly, overnight. It is used to give a simple way of comparing the cost of different power plant projects or technologies, expressed as a ratio against the maximum power the finished plant can deliver. This description is adapted from Wikipedia contributors under CC BY-SA 4.0; changes were made. https://creativecommons.org/licenses/by-sa/4.0/
Facts
Concept Domain Sources
1. Wikipedia: Overnight cost
IntroductionQuote, Introduction
The overnight capital cost is a term used in the power generation industry.