The Tesla-built lithium-ion battery near Jamestown, South Australia, completed at 100 megawatts and 129 megawatt-hours in November 2017 and expanded in September 2020 to 150 megawatts and 193.5 megawatt-hours. Its owner and operator Neoen calls it the world's first big battery; at completion it was widely described as the largest lithium-ion battery in the world, a title larger installations have since taken. It sells grid services, above all fast frequency response, alongside stored energy.

Facts
Facility Type
Battery storage facility 1
Location
Jamestown, South Australia, Australia 1
Capacity (MW)
150 1
Discharge power after the September 2020 expansion; stored energy is 193.5 MWh. Originally 100 MW and 129 MWh in 2017.
Commissioned Year
2017 1
Cross-Tradition Connections

Associated With

Sources
1. Hornsdale Power Reserve Official Site
NeoenOverview
Quote, Overview
The first 100 MW/129 MWh was completed in November 2017.
View the Source
1. Hornsdale Power Reserve Official Site
NeoenLocation
Quote, Location
approximately 15km north of Jamestown
View the Source
Comments (0)
No comments yet. Be the first to share a thought.
Reader Challenges (0 open reader challenges)
No disputes yet. Spotted an error or a better source? Open the first one.

View At A Past Year

The atlas records no dated fact of its own for this entry, so there is no other year to choose.